Northern Water Plant construction progressing well

Construction of the $94 million Northern Water Plant is progressing well, with more than 60% of the project complete.

The facility is taking shape, with earthworks and structures mostly finished. Attention has now turned to mechanical and electrical fit-out inside the buildings.

Installation of the water treatment and Class A recycling equipment has started. Most of the components have been manufactured in Australia but some specialist items are being imported from Germany.

Commissioning the plant will begin mid-2012 once construction has been completed and all systems have been checked and tested.