Newtown feeder main: progress update

This week’s wet weather has slowed progress on the Newtown feeder main upgrade project.

To date, 215 metres of the 990-metre new pipe section have been laid.

Today (11 April 2014) our contractors are laying a temporary asphalt seal over the pipe trench. This will create a better surface for after-hours and weekend traffic.

Work will continue next week west of Queens Park Bridge, adjacent the golf course.

For more detail, please refer to the project page.