Armstrong Creek sewerage connection

Barwon Water will connect key Armstrong Creek sewerage infrastructure next week.

It's a major project: connecting the sewer network in the new development to the 1.65 metre diameter sewer main that links Geelong to the Black Rock treatment facility in Connewarre.

Four pumps will run around-the-clock, diverting sewage through a temporary bypass pipeline around the connection point. Flows of up to 800 litres per second are expected.

Works are being carried out on Harvey Avenue, north of Warralily Boulevard.

We expect some odour at the site while works are underway.