| Contract No. | Title | Contract Expires | Price |
| 11006 | Switchboard Replacements - Sewer - 2009/10 | 2010-05-31 |
$173,668.00 |
| 11003 | Supply, Delivery & Installation of Laptops/Tablets | 2010-06-30 |
$340,509.30 |
| 10986 | Sewer Mains Rehabilitation 09/10 Separable Portion A | 2010-06-30 |
$1,511,062.71 |
| 10983 | Armstrong Creek Water Recycling Scheme: Stage 1: ASR Concept Design | 2011-06-30 |
$277,577.30 |
| 10976 | Winchelsea Feeder Main - 2.5km of 450mm MSCL Pipe | 2010-06-30 |
$825,330.00 |
| 10974 | Construction of Lara Reticulation Connection - Windermere Rd | 2010-06-30 |
$109,389.50 |
| 10972 | Asset Revaluation 2009/10 | 2010-06-30 |
$130,674.00 |
| 10970 | Anglesea Borefield Project - Installation of Monitoring Bores | 2010-06-30 |
$201,784.00 |
| 10969 | Pipe Supply for Callaghans Creek | 2010-06-30 |
$455,097.50 |
| 10963 | Winchelsea Feeder Main | 2010-06-30 |
$647,713.00 |
| 10956 | Functional Design - Armstrong Creek Recycled Water | 2010-06-30 |
$308,052.00 |
| 10954 | Construction of Jetty Road Feeder Main Stage 1 | 2010-06-18 |
$290,541.90 |
| 10953 | Anglesa Borefield Project - Extension of Borefield Collection Pipeline 3.5km | 2009-12-31 |
$654,056.70 |
| 10944 | Breamlea Retaining Wall & Rising Main Removal | 2010-06-30 |
$267,234.00 |
| 10935 | Northen Water Plant Peer Advice | 2010-06-30 |
$418,321.20 |
| 10933 | Anglesea Borefield Project - Supply and Delivery of 3.5km Pipe and Fittings | 2010-06-30 |
$862,961.00 |
| 10932 | Winchelsea Feeder Main - Pipe Supply Contract | 2009-06-30 |
$137,530.80 |
| 10932 | Leopold Feeder Main - Melaluka Road | 2010-06-30 |
$137,530.80 |
| 10930 | Wurdee Boluc Inlet Channel Relining - Stage 3 | 2009-06-30 |
$995,500.00 |
| 10919 | Design of Bellarine Transfer Main Stage 5a | 2009-06-30 |
$114,105.20 |
| 10918 | Pipeline & Booster P/S Design - Jan Juc HHL Water Supply | 2009-06-30 |
$160,561.70 |
| 10916 | Pipeline Design - Bellarine Transfer Main Stage 5b | 2010-06-30 |
$172,165.40 |
| 10910 | Colac Fluoride and Alum Dosing Facility | 2010-06-30 |
$1,942,472.40 |
| 10908 | Highton Feeder Main Replacement Stage 1 | 2010-06-30 |
$1,149,695.80 |
| 10907 | BRWRP - Supply & Delivery of 18 Decanter Actuator Units | 2009-06-30 |
$271,656.00 |
| 10906 | Wind Power Development Program - Functional Design | 2009-06-30 |
$186,725.00 |
| 10905 | Supply and Delivery of MSCL Pipe | 2009-06-30 |
$4,718,007.35 |
| 10894 | Aquifer Storage & Recovery - Investigation Project - Implementation of Community & Stakeholder Engagement Plan | 2011-06-30 |
$443,126.00 |
| 10893 | Ocean Grove SPS No. 1 | 2009-12-31 |
$190,410.00 |
| 10888 | Highton Feeder Main - Supply & Delivery of 960mm MSCL Pipe | 2010-06-30 |
$1,606,736.00 |
| 10874 | Spring Creek Urban Growth Area | 2009-06-30 |
$168,534.00 |
| 10873 | Bannockburn Aeration Upgrade | 2010-06-30 |
$102,124.00 |
| 10872 | Additional Outfall Sewer Rehabilitation | 2010-06-30 |
$675,508.92 |
| 10871 | Outfall Sewer Manhole Rehabilitation | 2010-06-30 |
$323,433.00 |
| 10869 | Detailed Design - Armstrong Creek West Branch Sewer | 2009-06-30 |
$162,575.00 |
| 10857 | Outfall Sewer Cleaning - Reserve Rd to Black Rock | 2010-07-31 |
Schedule of Rates |
| 10856 | Anglesea Borefield Project - Riserless Inflatable Packer Systems | 2010-06-30 |
$1,632,764.68 |
| 10854 | Supply & Delivery of Submersible Pump Sets - Bellarine Sewerage Strategy | 2009-06-30 |
$377,201.00 |
| 10849 | Colac No 1 Rising Main Replacement - Construction Contract | 2009-05-30 |
$596,559.70 |
| 10848 | Colac No 1 Rising Main Replacement - Supply, Delivery and Unloading of Pipes and Fittings | 2009-06-30 |
$542,326.00 |
| 10842 | Birregurra Sewerage Scheme Detailed Design and Bannockburn Water Reclamation Plant - Treatment Upgrade Detailed Design | 2010-06-30 |
$616,763.00 |
| 10840 | Detailed Design - Armstrong Creek Water & Sewerage Stages 1 & 2 | 2009-06-30 |
$1,185,730.70 |
| 10835 | Construction of Barwon Heads No.11 Rising Main | 2010-06-30 |
$2,116,587.00 |
| 10834 | Design of Barwon Heads Rising Main 1 and Ocean Grove Rising Main 2 - West Section | 2009-06-30 |
$135,410.00 |
| 10830 | Switchboard Replacements - Sewer - 2008/2009 | 2009-06-30 |
$139,915.00 |
| 10829 | Geelong Fluoride and Alum Dosing Facilities | 2010-06-30 |
$2,189,942.70 |
| 10828 | Watersmart Residential Behaviour Change Project | 2010-06-30 |
$400,716.00 |
| 10821 | Leopold Pressure Reduction | 2010-06-30 |
$121,000.00 |
| 10815 | Wye River & Separation Creek Sewerage Scheme - Functional Design | 2009-06-30 |
$379,410.00 |
| 10814 | Main Outfall Sewer Duplication Option Assessment and Functional Design - Proposal for Provision of Consulting Technical Services | 2009-06-30 |
$213,735.00 |
| 10812 | Barwon Water Capital Delivery Strategy | 2009-06-30 |
$153,381.00 |
| 10812 | Barwon Water Capital Works Delivery Strategy | 2009-06-30 |
$153,381.00 |
| 10806 | Provision of Learning Development | 2010-06-30 |
$142,450.00 |
| 10789 | Chemical Treatment of Tree Roots Within A Gravity Sewer System | 2011-08-27 |
Schedule of Rates |
| 10786 | Construction of Torquay HL Feeder Main - Coombes Rd to Beacon Blvd | 2009-06-30 |
$187,044.00 |
| 10780 | Supply, Delivery and Unloading of Casing for Observation Bores (South Newlingrook) | 2008-06-30 |
$151,637.95 |
| 10775 | Barwon Water WTP Fluoride Implementation Wurdee Boluc WTP and Moorabool WTP Work Plan | 2009-06-30 |
$195,371.00 |
| 10770 | Outfall Sewer Rehabilitation | 2009-06-30 |
$3,482,002.00 |
| 10769 | Construction of Moorabool Street Bridge Walkway | 2009-09-30 |
$213,761.00 |
| 10768 | Waurn Ponds Feeder Main, Ficinia Mews to Pioneer Rd Construction | 2010-06-30 |
$757,691.00 |
| 10757 | Bellarine Sewerage System Odour & Corrosion Control | 2008-09-30 |
$153,000.00 |
| 10751 | Barwon Heads No 11 Rising Main - Supply, Delivery and Unloading of Pipes and Fittings | 2009-06-30 |
$2,691,932.00 |
| 10750 | Construction of Ocean Grove Pump Station 4 Emergency Storage | 2010-06-30 |
$3,322,693.00 |
| 10748 | Anglesea Borefield Project: Supply of Bore Pumps | 2009-06-30 |
$1,430,872.30 |
| 10739 | Anglesea Borefield Project - Construction of Pretreatment Plant, Transfer Pump Station and Bore Sites | 2010-06-30 |
$9,924,781.00 |
| 10731 | Construction of the Northern Flow Retarding Facility Stage 2 | 2010-06-30 |
$2,908,767.00 |
| 10723 | Anglesea Borefield Project: Supply of Axially Split Case Transfer Pumps | 2009-06-30 |
$209,722.00 |
| 10720 | Anglesea Borefield Project - Construction of Transfer Pipeline | 2009-06-30 |
$4,432,633.00 |
| 10719 | Construction of Borefield Collection Pipeline | 2009-06-30 |
$2,313,214.00 |
| 10712 | Switchboard Replacements - Sewer - 2007/08 | 2008-06-30 |
$159,038.00 |
| 10710 | Anglesea Borefield - Supply, Delivery and Unloading of Ductile Iron Fittings | 2008-06-30 |
$181,071.00 |
| 10709 | Visitor Centre Upgrade Black Rock Water Reclamation Plant | 2008-06-30 |
$150,000.00 |
| 10707 | Anglesea Borefield - Supply, Delivery and Unloading of Steel Pipe | 2008-06-30 |
$3,648,198.00 |
| 10706 | Anglesea Borefield - Supply, Delivery and Unloading of GRP Pipe | 2008-06-30 |
$2,999,943.00 |
| 10703 | Kawarren Long-Term Pump Test | 2009-12-06 |
$230,087.00 |
| 10702 | Wurdee Boluc Inlet Channel Reconstruction Stage 2 | 2008-06-30 |
$1,407,813.00 |
| 10695 | Anglesea Borefield - Stage 2 | 2009-06-30 |
$2,262,414.00 |
| 10694 | Armstrong Creek Water & Sewerage System Design | 2008-06-30 |
$115,060.00 |
| 10693 | Barwon Downs Groundwater Observation Bores Refurbishment | 2009-06-30 |
Schedule of Rates |
| 10690 | Shallow Bore Construction Program | 2009-06-30 |
Schedule of Rates |
| 10689 | South Newlingrook Investigative Drilling | 2009-06-30 |
Schedule of Rates |
| 10689 | South Newlingrook Investigative Drilling | 2009-06-30 |
$1,067,550.00 |
| 10687 | Water Supply Improvements | 2009-06-30 |
$136,950.00 |
| 10678 | Colac Retic Improvements Stage 3 - Construction of 2,112m of 225mm Diameter Feeder Main^ Hearn St & Forrest St Colac | 2008-12-31 |
$426,157.00 |
| 10671 | South East Feeder Main - Supply, Delivery & Unloading of Pipes and Fittings | 2008-06-30 |
$195,643.00 |
| 10668 | Black Rock Water Reclamation Plant Aquifer Storage and Recovery - Stage 2 | 2009-06-30 |
$857,835.00 |
| 10667 | Renewal of Reticulation Gravity Sewer Mains, Multi Year Contract - Various Locations | 2010-06-30 |
Schedule of Rates |
| 10664 | Provision of Plant Hire (Wet Hire) | 2010-10-31 |
Schedule of Rates |
| 10657 | Rehabilitation of Outfall Sewer and Western Gully Submain | 2009-01-06 |
$2,606,359.00 |
| 10648 | Point Lonsdale Water Supply Improvements | 2008-06-30 |
$136,367.00 |
| 10643 | Newlingrook & Gellibrand Groundwater Management Areas Detailed Investigations | 2009-06-30 |
$1,848,319.00 |
| 10636 | Wurdee Boluc Upgrade Stage 2 - Pipe Supply | 2008-06-30 |
Schedule of Rates |
| 10634 | Detailed Design of Emergency Storage Facility for Pump Station No. 4 - Bonnyvale Road, Ocean Grove | 2008-06-30 |
$179,698.00 |
| 10630 | Ocean Grove Rising Main No. 2 - Functional Design | 2008-06-30 |
$276,705.00 |
| 10629 | Painkalac Dam Upgrade - Hydraulic Model Study | 2008-06-30 |
$106,650.00 |
| 10625 | Wurdee Boluc Water Treatment Plant Lime Clarification Design | 2009-06-30 |
$173,569.00 |
| 10613 | Anglesea Borefield Project Investigative Drilling | 2008-06-30 |
Schedule of Rates |
| 10607 | George Street Feeder Main - Construction of 1.4 km of 660mm MSCL Pipeline | 2008-06-30 |
$878,922.00 |
| 10605 | Provision of Vehicle and Plant Maintenance Services | 2010-06-30 |
Schedule of Rates |
| 10600 | Alvie Basin Design and Installation of a Liner and Cover | 2008-06-30 |
$877,353.40 |
| 10598 | Barwon Downs Groundwater Project - Stage 3 Hydrogeological Consultancy | 2008-06-30 |
$367,510.00 |
| 10590 | Queenscliff Basin, Design and Installation of Liner and Cover^ Including Associated Construction Works | 2009-06-30 |
$3,238,205.00 |
| 10588 | Montpellier Service Basin No 4 Design and Installation of Liner and Cover and Associated Construction Works | 2009-06-30 |
$3,673,012.20 |
| 10585 | Provision of Traffic Management Services | 2010-06-30 |
Schedule of Rates |
| 10584 | Colac Water Reclamation Plant - Duplication of Ultraviolet Disinfection Channel | 2008-06-30 |
$330,700.27 |
| 10583 | Colac Water Reclamation Plant - Ultraviolet Disinfection Duplication Project | 2008-06-30 |
$281,600.00 |
| 10581 | Wurdee Boluc Washwater Treatment Upgrade | 2008-06-30 |
$326,040.00 |
| 10580 | Detailed Design of Northern Flow Retarding Facility Stage 2 | 2008-06-30 |
$280,266.00 |
| 10574 | North West Torquay Sewerage Scheme - Construction of Pump Station and Storage | 2008-06-30 |
$693,971.30 |
| 10570 | Design, Supply and Installation of the Montpellier Mini-Hydro | 2008-06-30 |
$291,280.00 |
| 10569 | Apollo Bay Water Reclamation Plant Construction of a Flow Equlisation Tank | 2008-06-30 |
$1,428,918.00 |
| 10565 | Technical Services Panel Contract | 2010-01-21 |
Schedule of Rates |
| 10559 | Colac Transfer Main Duplication Stage 4 Construction of 1.8km of 660mm MSCL Pipeline | 2008-06-30 |
$665,709.00 |
| 10547 | Dog Rocks Road High Level Pump Station Upgrade, Batesford | 2008-06-30 |
$273,445.00 |
| 10545 | Construction of Torquay No 1 Sewerage Pumping Station | 2008-12-31 |
$745,211.00 |
| 10538 | Design and Construction of 500KL Water Storage Tank - Holliday Road, Lorne | 2008-06-30 |
$833,492.00 |
| 10521 | Water Main Replacement Services - Various Locations | 2008-06-30 |
Schedule of Rates |
| 10515 | Pipe/Pedestrian Bridge, Deep Creek^ Torquay | 2008-06-30 |
$273,747.00 |
| 10513 | Wurdee Boluc Upgrade Stage 2 Backwash Pumpstation and Filter Pipework Modifications | 2008-06-30 |
$5,174,960.00 |
| 10511 | Reinstatement of Nature Strips | 2009-06-30 |
Schedule of Rates |
| 10507 | Wurdee Boluc Upgrade Stage 1 Washwater Supply/Clearwater Storage Tank | 2008-09-30 |
$1,324,453.00 |
| 10503 | Design & Construct Odour Control Facility at the Black Rock Water Reclamation Plant | 2008-06-30 |
$1,800,260.00 |
| 10502 | Residential Customer Satisfaction Survey | 2011-06-30 |
$181,335.00 |
| 10498 | Design and Construction of 650KL Water Storage Tank Skenes Crek | 2008-09-06 |
$1,029,270.00 |
| 10495 | Replacement of Fencing at Anakie/Stoney Creek | 2008-07-31 |
Schedule of Rates |
| 10482 | Stationery Contract 2006 - 2008 | 2008-12-31 |
$300,000.00 |
| 10299 | Construction of Coastal Sewer Inlet Works at Black Rock Water Reclamation Plant | 2008-06-30 |
$2,845,453.00 |
| 10203 | Service Maintenance - Corporate Buildings | 2008-06-30 |
$166,152.00 |
| 10187 | Supply & Delivery of Bulk Liquid Oxygen & Carbon Dioxide | 2010-06-30 |
Schedule of Rates |
| 458 | Customer Perception Survey | 2012-03-12 |
$125,060.00 |
| 343 | Apollo Bay WTP Membrane Replacement | 2011-06-30 |
$238,791.00 |
| 259 | Cleaning Sewer Pipelines | 2010-06-30 |
$142,335.00 |
| 254 | Colac Water Supply Augmentation Investigation | 2010-12-29 |
$152,618.40 |
| 248 | Root Cutting of Sewer Mains | 2012-05-16 |
Schedule of Rates |